Q)

It takes 4 men 6 hours to repair a road. How long will it take 7 mens to do the job if they work at the same rate ?

$\begin{array}{1 1} 3\;hr \\ 3 \frac{2}{5} \\ 3 \frac{3}{7} \\ 4\;hr \end{array} $