A can do a certain work in 25 days which B alone can do in 20 days. A stared the work and was joined by B after 10 days. The work was completed in
( A ) 15 1/3 days
( B ) 14 1/3 days
( C ) 16 2/3 days
( D ) 18 2/3 days